Calculation guide
yieldNeeded = cost/(price-handling)
Inputs
Input cost per hectare
Example entry 900.0 (in the selected currency).
Sale price per tonne
Example entry 220.0 (in the selected currency).
Variable harvest cost per tonne
Example entry 20.0 (in the selected currency).
Worked example
| Input | Value |
|---|---|
| Input cost per hectare | 900 |
| Sale price per tonne | 220 |
| Variable harvest cost per tonne | 20 |
| Result | Value |
|---|---|
| Break-even tonnes per hectare | 4.5 |
Calculation steps
Break-even tonnes per hectare = (Input cost per hectare ÷ (Sale price per tonne − Variable harvest cost per tonne))
(900 ÷ (220 − 20)) = 4.5
Interpreting the result
A saleable yield below the threshold leaves the entered crop inputs uncovered.
How each input affects this example
Each row starts from the worked example and changes one input.
| Input | Original input | New input | Affected result | Original result | New result |
|---|---|---|---|---|---|
| Input cost per hectare | 900 | 990 | Break-even tonnes per hectare | 4.5 | 4.95 |
| Sale price per tonne | 220 | 242 | Break-even tonnes per hectare | 4.5 | 4.054054 |
| Variable harvest cost per tonne | 20 | 22 | Break-even tonnes per hectare | 4.5 | 4.545455 |