Subcontractor payment schedule after retention · Calculation guide

Withhold the same percentage of each chronological interim invoice.

Calculation guide

Release all accumulated retention in a separate final payment after the last invoice.

interim(t) = invoice(t) × (1−retention). final release = Σ retained(t).

Inputs

Retention rate (%)

Example entry 10 %. Allowed range 0 to 100.

Gross invoice

Example entry 5000 (in the selected currency).

Worked example

InputValue
Retention rate (%)10%

Interim invoices in order

Gross invoice
4,000
6,000
ResultValue
Interim payments total9,000
Final retention release1,000

How each input affects this example

Each row starts from the worked example and changes one input.

InputOriginal inputNew inputAffected resultOriginal resultNew result
Retention rate (%)10%11%Interim payments total9,0008,900
Gross invoice (row 1)4,0004,400Interim payments total9,0009,360