Calculation guide
Enter the one-sided service z-score. Round protection and the complete reorder point upward to whole units.
Safety stock units = round up(Service z-score × Units demanded per day × Lead time standard deviation in days). Reorder point units = round up(Units demanded per day × Mean lead time in days + Service z-score × Units demanded per day × Lead time standard deviation in days)
Inputs
Units demanded per day
Example entry 10.
Mean lead time in days
Example entry 5.
Lead time standard deviation in days
Example entry 2.
Service z-score
Example entry 1.645.
Worked example
| Input | Value |
|---|---|
| Units demanded per day | 10 |
| Mean lead time in days | 5 |
| Lead time standard deviation in days | 2 |
| Service z-score | 1.645 |
| Result | Value |
|---|---|
| Safety stock units | 33 |
| Reorder point units | 83 |
Calculation steps
Safety stock units = round up(((Service z-score × Units demanded per day) × Lead time standard deviation in days))
round up(((1.645 × 10) × 2)) = 33
Reorder point units = round up(((Units demanded per day × Mean lead time in days) + ((Service z-score × Units demanded per day) × Lead time standard deviation in days)))
round up(((10 × 5) + ((1.645 × 10) × 2))) = 83
How each input affects this example
Each row starts from the worked example and changes one input.
| Input | Original input | New input | Affected result | Original result | New result |
|---|---|---|---|---|---|
| Units demanded per day | 10 | 11 | Safety stock units | 33 | 37 |
| Mean lead time in days | 5 | 6 | Reorder point units | 83 | 93 |
| Lead time standard deviation in days | 2 | 3 | Safety stock units | 33 | 50 |
| Service z-score | 1.645 | 2.645 | Safety stock units | 33 | 53 |