Public project benefit-cost ratio · Calculation guide

Use monetized incremental benefits and resource costs against the same baseline, in consistent prices.

Calculation guide

Discount year-end amounts; initial costs occur today.

bcr = PV(benefits)/(initial + PV(costs)) · npv = PV(benefits) − initial − PV(costs)

Inputs

Initial public investment

Example entry 100000.0 (in the selected currency).

Annual social discount rate (%)

Example entry 10.0 %. Allowed range 0 to 100.

Monetized annual benefits

Example entry 88000.0 (in the selected currency).

Incremental annual costs

Example entry 11000.0 (in the selected currency).

Worked example

InputValue
Initial public investment100,000
Annual social discount rate (%)10%

Appraisal years

Monetized annual benefitsIncremental annual costs
88,00011,000
96,80012,100
ResultValue
Discounted benefit-cost ratio1.333333
Net present benefit40,000

Interpreting the result

A ratio above 1 means discounted, monetized benefits exceed the discounted project costs.

How each input affects this example

Each row starts from the worked example and changes one input.

InputOriginal inputNew inputAffected resultOriginal resultNew result
Initial public investment100,000110,000Discounted benefit-cost ratio1.3333331.230769
Annual social discount rate (%)10%11%Discounted benefit-cost ratio1.3333331.31833
Monetized annual benefits (row 1)88,00096,800Discounted benefit-cost ratio1.3333331.4
Incremental annual costs (row 1)11,00012,100Discounted benefit-cost ratio1.3333331.322314
Public project benefit-cost ratio →