Public-private partnership availability payment · Calculation guide

Apply the contractual availability fraction to the indexed base fee.

Calculation guide

Deduct performance penalties after availability, with a zero payment floor.

pay = max(0,base*index*available/100-penalty)

Inputs

Base period fee

Example entry 100000.0 (in the selected currency).

Contractual index multiplier

Example entry 1.05. Minimum 1e-12.

Payable availability (%)

Example entry 95.0 %. Allowed range 0 to 100.

Additional deductions

Example entry 2000.0 (in the selected currency).

Worked example

InputValue
Base period fee100,000
Contractual index multiplier1.05
Payable availability (%)95%
Additional deductions2,000
ResultValue
Net availability payment97,750

Calculation steps

Net availability payment = max(0, ((((Base period fee × Contractual index multiplier) × Payable availability (%)) ÷ 100) − Additional deductions))

max(0, ((((100,000 × 1.05) × 95) ÷ 100) − 2,000)) = 97,750

Interpreting the result

Higher availability raises the contracted payment before any extra performance deductions.

How each input affects this example

Each row starts from the worked example and changes one input.

InputOriginal inputNew inputAffected resultOriginal resultNew result
Base period fee100,000110,000Net availability payment97,750107,725
Contractual index multiplier1.052.05Net availability payment97,750192,750
Payable availability (%)95%85%Net availability payment97,75087,250
Additional deductions2,0002,200Net availability payment97,75097,550