Project completion delay cost · Calculation guide

Accumulate incremental site overhead, foregone net operating cash and simple carrying interest during the delay.

Calculation guide

cost = days*(overhead+lost+debt*rate/100/basis)

Inputs

Delay in days

Example entry 90.0. Use whole numbers.

Daily extra overhead

Example entry 1000.0 (in the selected currency).

Daily lost net cash flow

Example entry 2000.0 (in the selected currency).

Outstanding funded debt

Example entry 1000000.0 (in the selected currency).

Annual interest (%)

Example entry 4.0 %. Allowed range 0 to 100.

Day-count denominator

Example entry 360.0. Minimum 1. Use whole numbers.

Worked example

InputValue
Delay in days90
Daily extra overhead1,000
Daily lost net cash flow2,000
Outstanding funded debt1,000,000
Annual interest (%)4%
Day-count denominator360
ResultValue
Incremental delay cost280,000

Calculation steps

Incremental delay cost = (Delay in days × ((Daily extra overhead + Daily lost net cash flow) + (((Outstanding funded debt × Annual interest (%)) ÷ 100) ÷ Day-count denominator)))

(90 × ((1,000 + 2,000) + (((1,000,000 × 4) ÷ 100) ÷ 360))) = 280,000

Interpreting the result

Compare this amount with contractual delay compensation or a mitigation budget over the same period.

How each input affects this example

Each row starts from the worked example and changes one input.

InputOriginal inputNew inputAffected resultOriginal resultNew result
Delay in days9099Incremental delay cost280,000308,000
Daily extra overhead1,0001,100Incremental delay cost280,000289,000
Daily lost net cash flow2,0002,200Incremental delay cost280,000298,000
Outstanding funded debt1,000,0001,100,000Incremental delay cost280,000281,000
Annual interest (%)4%5%Incremental delay cost280,000282,500
Day-count denominator360396Incremental delay cost280,000279,090.909091