Profitability index under capital rationing · Calculation guide

Compare the present value of project inflows with the initial outlay and available budget.

Calculation guide

Ranking by index assumes divisible independent projects.

Profitability index = Present value of future net inflows / Initial outlay. Fundable project share = 100 × min(1,Available budget / Initial outlay). NPV of fundable share = (Present value of future net inflows − Initial outlay) × Fundable project share / 100

Inputs

Present value of future net inflows

Example entry 1250 (in the selected currency).

Initial outlay

Example entry 1000 (in the selected currency).

Available budget

Example entry 800 (in the selected currency).

Worked example

InputValue
Present value of future net inflows1,250
Initial outlay1,000
Available budget800
ResultValue
Profitability index1.25
Fundable project share80%
NPV of fundable share200

Calculation steps

Profitability index = (Present value of future net inflows ÷ Initial outlay)

(1,250 ÷ 1,000) = 1.25

Fundable project share = (100 × min(1, (Available budget ÷ Initial outlay)))

(100 × min(1, (800 ÷ 1,000))) = 80%

NPV of fundable share = (((Present value of future net inflows − Initial outlay) × Fundable project share) ÷ 100)

(((1,250 − 1,000) × 80) ÷ 100) = 200

How each input affects this example

Each row starts from the worked example and changes one input.

InputOriginal inputNew inputAffected resultOriginal resultNew result
Present value of future net inflows1,2501,375Profitability index1.251.375
Initial outlay1,0001,100Profitability index1.251.136364
Available budget800880Fundable project share80%88%
Profitability index under capital rationing →