Calculation guide
Compare with standard quantity allowed for actual output. Positive cost variances are unfavorable.
Price variance = Actual material quantity used × (Actual unit price − Standard unit price). Usage variance = (Actual material quantity used − Standard quantity for actual output) × Standard unit price. Total material cost variance = Price variance + Usage variance
Inputs
Actual material quantity used
Example entry 110.
Standard quantity for actual output
Example entry 100.
Actual unit price
Example entry 5.5 (in the selected currency).
Standard unit price
Example entry 5 (in the selected currency).
Worked example
| Input | Value |
|---|---|
| Actual material quantity used | 110 |
| Standard quantity for actual output | 100 |
| Actual unit price | 5.5 |
| Standard unit price | 5 |
| Result | Value |
|---|---|
| Price variance | 55 |
| Usage variance | 50 |
| Total material cost variance | 105 |
Calculation steps
Price variance = (Actual material quantity used × (Actual unit price − Standard unit price))
(110 × (5.5 − 5)) = 55
Usage variance = ((Actual material quantity used − Standard quantity for actual output) × Standard unit price)
((110 − 100) × 5) = 50
Total material cost variance = (Price variance + Usage variance)
(55 + 50) = 105
How each input affects this example
Each row starts from the worked example and changes one input.
| Input | Original input | New input | Affected result | Original result | New result |
|---|---|---|---|---|---|
| Actual material quantity used | 110 | 121 | Price variance | 55 | 60.5 |
| Standard quantity for actual output | 100 | 110 | Usage variance | 50 | 0 |
| Actual unit price | 5.5 | 6.5 | Price variance | 55 | 165 |
| Standard unit price | 5 | 6 | Price variance | 55 | -55 |