Material price and usage variance · Calculation guide

Use actual material consumed for both variances.

Calculation guide

Compare with standard quantity allowed for actual output. Positive cost variances are unfavorable.

Price variance = Actual material quantity used × (Actual unit price − Standard unit price). Usage variance = (Actual material quantity used − Standard quantity for actual output) × Standard unit price. Total material cost variance = Price variance + Usage variance

Inputs

Actual material quantity used

Example entry 110.

Standard quantity for actual output

Example entry 100.

Actual unit price

Example entry 5.5 (in the selected currency).

Standard unit price

Example entry 5 (in the selected currency).

Worked example

InputValue
Actual material quantity used110
Standard quantity for actual output100
Actual unit price5.5
Standard unit price5
ResultValue
Price variance55
Usage variance50
Total material cost variance105

Calculation steps

Price variance = (Actual material quantity used × (Actual unit price − Standard unit price))

(110 × (5.5 − 5)) = 55

Usage variance = ((Actual material quantity used − Standard quantity for actual output) × Standard unit price)

((110 − 100) × 5) = 50

Total material cost variance = (Price variance + Usage variance)

(55 + 50) = 105

How each input affects this example

Each row starts from the worked example and changes one input.

InputOriginal inputNew inputAffected resultOriginal resultNew result
Actual material quantity used110121Price variance5560.5
Standard quantity for actual output100110Usage variance500
Actual unit price5.56.5Price variance55165
Standard unit price56Price variance55-55
Material price and usage variance →