Calculation guide
This all-in definition includes purchased charging power.
Inputs
Storage capital cost
Example entry 300000.0 (in the selected currency).
Annual fixed operating cost
Example entry 10000.0 (in the selected currency).
Useful life (years)
Example entry 10.0. Minimum 1. Use whole numbers.
Annual discount rate (%)
Example entry 0.0 %. Allowed range 0 to 100.
Annual delivered MWh
Example entry 1000.0. Minimum 1e-12.
Round-trip efficiency (%)
Example entry 80.0 %. Allowed range 1e-12 to 100.
Charging price per MWh
Example entry 40.0 (in the selected currency).
Worked example
| Input | Value |
|---|---|
| Storage capital cost | 300,000 |
| Annual fixed operating cost | 10,000 |
| Useful life (years) | 10 |
| Annual discount rate (%) | 0% |
| Annual delivered MWh | 1,000 |
| Round-trip efficiency (%) | 80% |
| Charging price per MWh | 40 |
| Result | Value |
|---|---|
| All-in cost per MWh delivered | 90 |
Calculation steps
All-in cost per MWh delivered = (((payment(Storage capital cost, (12 × Annual discount rate (%)), Useful life (years)) + Annual fixed operating cost) ÷ Annual delivered MWh) + (Charging price per MWh ÷ (Round-trip efficiency (%) ÷ 100)))
(((payment(300,000, (12 × 0), 10) + 10,000) ÷ 1,000) + (40 ÷ (80 ÷ 100))) = 90
Interpreting the result
Lower efficiency increases the charging energy required for each delivered MWh.
How each input affects this example
Each row starts from the worked example and changes one input.
| Input | Original input | New input | Affected result | Original result | New result |
|---|---|---|---|---|---|
| Storage capital cost | 300,000 | 330,000 | All-in cost per MWh delivered | 90 | 93 |
| Annual fixed operating cost | 10,000 | 11,000 | All-in cost per MWh delivered | 90 | 91 |
| Useful life (years) | 10 | 11 | All-in cost per MWh delivered | 90 | 87.272727 |
| Annual discount rate (%) | 0% | 1% | All-in cost per MWh delivered | 90 | 91.674623 |
| Annual delivered MWh | 1,000 | 1,100 | All-in cost per MWh delivered | 90 | 86.363636 |
| Round-trip efficiency (%) | 80% | 88% | All-in cost per MWh delivered | 90 | 85.454545 |
| Charging price per MWh | 40 | 44 | All-in cost per MWh delivered | 90 | 95 |