Calculation guide
Price the efficiency difference at the standard hourly rate. Positive cost differences are unfavorable.
Labour rate variance = Actual labour hours × (Actual hourly rate − Standard hourly rate). Labour efficiency variance = (Actual labour hours − Standard hours allowed) × Standard hourly rate. Total labour cost variance = Labour rate variance + Labour efficiency variance
Inputs
Actual labour hours
Example entry 52.
Standard hours allowed
Example entry 50.
Actual hourly rate
Example entry 22 (in the selected currency).
Standard hourly rate
Example entry 20 (in the selected currency).
Worked example
| Input | Value |
|---|---|
| Actual labour hours | 52 |
| Standard hours allowed | 50 |
| Actual hourly rate | 22 |
| Standard hourly rate | 20 |
| Result | Value |
|---|---|
| Labour rate variance | 104 |
| Labour efficiency variance | 40 |
| Total labour cost variance | 144 |
Calculation steps
Labour rate variance = (Actual labour hours × (Actual hourly rate − Standard hourly rate))
(52 × (22 − 20)) = 104
Labour efficiency variance = ((Actual labour hours − Standard hours allowed) × Standard hourly rate)
((52 − 50) × 20) = 40
Total labour cost variance = (Labour rate variance + Labour efficiency variance)
(104 + 40) = 144
How each input affects this example
Each row starts from the worked example and changes one input.
| Input | Original input | New input | Affected result | Original result | New result |
|---|---|---|---|---|---|
| Actual labour hours | 52 | 57 | Labour rate variance | 104 | 114 |
| Standard hours allowed | 50 | 55 | Labour efficiency variance | 40 | -60 |
| Actual hourly rate | 22 | 24 | Labour rate variance | 104 | 208 |