Job order cost from labour and overhead · Calculation guide

Apply overhead per direct labour hour and add direct material and labour.

Calculation guide

Divide by completed good units. Use one implementation of overhead to avoid double counting.

Total job cost = Direct materials + Direct labour hours × (Direct wage per hour + Applied overhead per direct labour hour). Cost per good unit = Total job cost / Good units completed

Inputs

Direct materials

Example entry 1000 (in the selected currency).

Direct labour hours

Example entry 40.

Direct wage per hour

Example entry 20 (in the selected currency).

Applied overhead per direct labour hour

Example entry 12 (in the selected currency).

Good units completed

Example entry 60. Use whole numbers.

Worked example

InputValue
Direct materials1,000
Direct labour hours40
Direct wage per hour20
Applied overhead per direct labour hour12
Good units completed60
ResultValue
Total job cost2,280
Cost per good unit38

Calculation steps

Total job cost = (Direct materials + (Direct labour hours × (Direct wage per hour + Applied overhead per direct labour hour)))

(1,000 + (40 × (20 + 12))) = 2,280

Cost per good unit = (Total job cost ÷ Good units completed)

(2,280 ÷ 60) = 38

How each input affects this example

Each row starts from the worked example and changes one input.

InputOriginal inputNew inputAffected resultOriginal resultNew result
Direct materials1,0001,100Total job cost2,2802,380
Direct labour hours4044Total job cost2,2802,408
Direct wage per hour2022Total job cost2,2802,360
Applied overhead per direct labour hour1213Total job cost2,2802,320
Good units completed6066Cost per good unit3834.545455