Istisna staged construction payments · Calculation guide

Enter payment percentages totaling 100%.

Calculation guide

Approved stages are payable at their contractual share of the fixed manufacture price. Later stages remain committed.

due = fixed price × Σ approved stage shares

Inputs

Fixed manufacture price

Example entry 100000 (in the selected currency).

Approved sequential stages

Example entry 2. Allowed range 0.0 to 120.0. Use whole numbers.

Stage share (%)

Example entry 30 %. Allowed range 0 to 100.

Worked example

InputValue
Fixed manufacture price100,000
Approved sequential stages2

Sequential contract stages

Stage share (%)
30%
40%
30%
ResultValue
Price due for approved stages70,000
Price for remaining stages30,000

How each input affects this example

Each row starts from the worked example and changes one input.

InputOriginal inputNew inputAffected resultOriginal resultNew result
Fixed manufacture price100,000110,000Price due for approved stages70,00077,000
Approved sequential stages23Price due for approved stages70,000100,000