Cost to complete versus certified work value · Calculation guide

Compare remaining contract value with estimated remaining cost.

Calculation guide

Use cumulative certified work before retention and the current revised total contract value.

Remaining value less cost to complete = ((Revised contract value − Cumulative certified work) − Estimated cost to complete). Uncertified contract value = (Revised contract value − Cumulative certified work)

Inputs

Revised contract value

Example entry 100000 (in the selected currency).

Cumulative certified work

Example entry 60000 (in the selected currency).

Estimated cost to complete

Example entry 45000 (in the selected currency).

Worked example

InputValue
Revised contract value100,000
Cumulative certified work60,000
Estimated cost to complete45,000
ResultValue
Remaining value less cost to complete-5,000
Uncertified contract value40,000

Calculation steps

Remaining value less cost to complete = ((Revised contract value − Cumulative certified work) − Estimated cost to complete)

((100,000 − 60,000) − 45,000) = -5,000

Uncertified contract value = (Revised contract value − Cumulative certified work)

(100,000 − 60,000) = 40,000

How each input affects this example

Each row starts from the worked example and changes one input.

InputOriginal inputNew inputAffected resultOriginal resultNew result
Revised contract value100,000110,000Remaining value less cost to complete-5,0005,000
Cumulative certified work60,00066,000Remaining value less cost to complete-5,000-11,000
Estimated cost to complete45,00049,500Remaining value less cost to complete-5,000-9,500
Cost to complete versus certified work value →