Cost overrun sponsor equity requirement · Calculation guide

Use the projected final cost and base budget on the same basis.

Calculation guide

Apply remaining contingency and committed incremental debt before sponsor equity.

equity = max(0,forecast-budget-reserve-debt)

Inputs

Forecast final cost

Example entry 1200000.0 (in the selected currency).

Original funded base budget

Example entry 1000000.0 (in the selected currency).

Unused contingency outside base

Example entry 60000.0 (in the selected currency).

Additional committed debt

Example entry 40000.0 (in the selected currency).

Worked example

InputValue
Forecast final cost1,200,000
Original funded base budget1,000,000
Unused contingency outside base60,000
Additional committed debt40,000
ResultValue
Required sponsor equity100,000

Calculation steps

Required sponsor equity = max(0, (((Forecast final cost − Original funded base budget) − Unused contingency outside base) − Additional committed debt))

max(0, (((1,200,000 − 1,000,000) − 60,000) − 40,000)) = 100,000

Interpreting the result

A positive result is the sponsor cash still required after contingency and committed debt are used.

How each input affects this example

Each row starts from the worked example and changes one input.

InputOriginal inputNew inputAffected resultOriginal resultNew result
Forecast final cost1,200,0001,320,000Required sponsor equity100,000220,000
Original funded base budget1,000,0001,100,000Required sponsor equity100,0000
Unused contingency outside base60,00066,000Required sponsor equity100,00094,000
Additional committed debt40,00044,000Required sponsor equity100,00096,000
Cost overrun sponsor equity requirement →