Calculation guide
Apply remaining contingency and committed incremental debt before sponsor equity.
equity = max(0,forecast-budget-reserve-debt)
Inputs
Forecast final cost
Example entry 1200000.0 (in the selected currency).
Original funded base budget
Example entry 1000000.0 (in the selected currency).
Unused contingency outside base
Example entry 60000.0 (in the selected currency).
Additional committed debt
Example entry 40000.0 (in the selected currency).
Worked example
| Input | Value |
|---|---|
| Forecast final cost | 1,200,000 |
| Original funded base budget | 1,000,000 |
| Unused contingency outside base | 60,000 |
| Additional committed debt | 40,000 |
| Result | Value |
|---|---|
| Required sponsor equity | 100,000 |
Calculation steps
Required sponsor equity = max(0, (((Forecast final cost − Original funded base budget) − Unused contingency outside base) − Additional committed debt))
max(0, (((1,200,000 − 1,000,000) − 60,000) − 40,000)) = 100,000
Interpreting the result
A positive result is the sponsor cash still required after contingency and committed debt are used.
How each input affects this example
Each row starts from the worked example and changes one input.
| Input | Original input | New input | Affected result | Original result | New result |
|---|---|---|---|---|---|
| Forecast final cost | 1,200,000 | 1,320,000 | Required sponsor equity | 100,000 | 220,000 |
| Original funded base budget | 1,000,000 | 1,100,000 | Required sponsor equity | 100,000 | 0 |
| Unused contingency outside base | 60,000 | 66,000 | Required sponsor equity | 100,000 | 94,000 |
| Additional committed debt | 40,000 | 44,000 | Required sponsor equity | 100,000 | 96,000 |
