Calculation guide
Add prevention and appraisal to internal and external failure costs to obtain total quality cost.
Inputs
Reworked units
Example entry 20. Use whole numbers.
Rework cost per unit
Example entry 5 (in the selected currency).
Scrapped units
Example entry 10. Use whole numbers.
Net scrap cost per unit
Example entry 12 (in the selected currency).
Externally failed units
Example entry 5. Use whole numbers.
Cost per external failure
Example entry 30 (in the selected currency).
Prevention cost
Example entry 100 (in the selected currency).
Appraisal cost
Example entry 80 (in the selected currency).
Worked example
| Input | Value |
|---|---|
| Reworked units | 20 |
| Rework cost per unit | 5 |
| Scrapped units | 10 |
| Net scrap cost per unit | 12 |
| Externally failed units | 5 |
| Cost per external failure | 30 |
| Prevention cost | 100 |
| Appraisal cost | 80 |
| Result | Value |
|---|---|
| Total quality cost | 550 |
| Internal failure cost | 220 |
| External failure cost | 150 |
Calculation steps
Total quality cost = (((((Reworked units × Rework cost per unit) + (Scrapped units × Net scrap cost per unit)) + (Externally failed units × Cost per external failure)) + Prevention cost) + Appraisal cost)
(((((20 × 5) + (10 × 12)) + (5 × 30)) + 100) + 80) = 550
Internal failure cost = ((Reworked units × Rework cost per unit) + (Scrapped units × Net scrap cost per unit))
((20 × 5) + (10 × 12)) = 220
External failure cost = (Externally failed units × Cost per external failure)
(5 × 30) = 150
How each input affects this example
Each row starts from the worked example and changes one input.
| Input | Original input | New input | Affected result | Original result | New result |
|---|---|---|---|---|---|
| Reworked units | 20 | 22 | Total quality cost | 550 | 560 |
| Rework cost per unit | 5 | 6 | Total quality cost | 550 | 570 |
| Scrapped units | 10 | 11 | Total quality cost | 550 | 562 |
| Net scrap cost per unit | 12 | 13 | Total quality cost | 550 | 560 |
| Externally failed units | 5 | 6 | Total quality cost | 550 | 580 |
| Cost per external failure | 30 | 33 | Total quality cost | 550 | 565 |
| Prevention cost | 100 | 110 | Total quality cost | 550 | 560 |
| Appraisal cost | 80 | 88 | Total quality cost | 550 | 558 |