Calculation guide
Add fixed change-order labour expenses separately.
Burdened change-order labour cost = (((Additional labour hours × Base wage per hour) × (1 + (Payroll burden on wages (%) ÷ 100))) + Fixed labour extras). Percentage-based labour burden = (((Additional labour hours × Base wage per hour) × Payroll burden on wages (%)) ÷ 100)
Inputs
Additional labour hours
Example entry 80.
Base wage per hour
Example entry 25 (in the selected currency).
Payroll burden on wages (%)
Example entry 30 %. Allowed range 0.0 to 500.0.
Fixed labour extras
Example entry 100 (in the selected currency).
Worked example
| Input | Value |
|---|---|
| Additional labour hours | 80 |
| Base wage per hour | 25 |
| Payroll burden on wages (%) | 30% |
| Fixed labour extras | 100 |
| Result | Value |
|---|---|
| Burdened change-order labour cost | 2,700 |
| Percentage-based labour burden | 600 |
Calculation steps
Burdened change-order labour cost = (((Additional labour hours × Base wage per hour) × (1 + (Payroll burden on wages (%) ÷ 100))) + Fixed labour extras)
(((80 × 25) × (1 + (30 ÷ 100))) + 100) = 2,700
Percentage-based labour burden = (((Additional labour hours × Base wage per hour) × Payroll burden on wages (%)) ÷ 100)
(((80 × 25) × 30) ÷ 100) = 600
How each input affects this example
Each row starts from the worked example and changes one input.
| Input | Original input | New input | Affected result | Original result | New result |
|---|---|---|---|---|---|
| Additional labour hours | 80 | 88 | Burdened change-order labour cost | 2,700 | 2,960 |
| Base wage per hour | 25 | 28 | Burdened change-order labour cost | 2,700 | 3,012 |
| Payroll burden on wages (%) | 30% | 33% | Burdened change-order labour cost | 2,700 | 2,760 |
| Fixed labour extras | 100 | 110 | Burdened change-order labour cost | 2,700 | 2,710 |