Activity-based costing pool allocation · Calculation guide

Allocate each activity pool using the cost object’s share of its driver.

Calculation guide

Each pool must have positive total activity. Sum the allocated amounts across pools.

Allocated cost = Σ pool cost × object activity / total activity

Inputs

Total activity pool cost

Example entry 1000 (in the selected currency).

Driver units for all objects

Example entry 100.

Driver units used by this object

Example entry 20.

Worked example

Activity cost pools

Total activity pool costDriver units for all objectsDriver units used by this object
1,00010020
1,500505
ResultValue
Activity costs allocated to object350
Pool cost assigned elsewhere2,150

How each input affects this example

Each row starts from the worked example and changes one input.

InputOriginal inputNew inputAffected resultOriginal resultNew result
Total activity pool cost (row 1)1,0001,100Activity costs allocated to object350370
Driver units for all objects (row 1)100110Activity costs allocated to object350331.818182
Driver units used by this object (row 1)2022Activity costs allocated to object350370
Activity-based costing pool allocation →